The minimum cost of complying with a 2013 federal court order to fix by 2030 some 1,019 Washington State Department of Transportation-owned culverts posing barriers to salmon passage will be a whopping $2.4 billion, lawmakers have learned. But “lack of future funding and technical complexity are creating obstacles to planning and delivery,” according to an agency presentation last week to the House Transportation Committee. Culverts are tunnel- or pipe-like structures embedded in soil to carry water, often salmon-bearing streams, under roads, railroads and trails.

WSDOT culvert at Fortson Creek on State Route 530 west of Darrington; before replacement - Source: WSDOT

Funding Sources Unclear Right Now
In an interview the Director of WSDOT’s Environmental Services Office Megan White, who led the agency presentation to the committee, said it’s not clear where the money might come from. But she said the first step this session is “talking to legislative leaders and decision makers about the challenge in front of us, in hopes there will be some focus” on developing a funding strategy.

$200M Eyed For ‘15-’17 Biennium
The agency is currently expecting to recommend inclusion of $200 million in in the 2015-17 state budget for court-ordered culvert work on project scoping, design and construction. WSDOT would expect to request successively higher amounts in following state budgets, and now has just about $20 million it can carry forward into the next budget for that, according to White. She added, “The level of funding goes beyond what the agency can provide from existing resources. We don’t want to be in the position of testing what non-compliance means,” with respect to the U.S. court order.

AG’s Office: Compliance Would Be A ‘Heavy Lift’
Senior Assistant Attorney General Joseph Shorin said the “sweeping” federal injunction poses a “heavy lift” for the state with a financial compliance burden that’s “extremely expensive.” Although the state is appealing, it also must at present proceed as if the ruling will stay in force, he said; there is no “stay” or suspension of the court’s directive during the appeal.

Public Data Ferret’s Washington State+Environment archive

Tribes and U.S. Sued State
In the case, U.S. v. Washington, 21 Native American tribes and the federal government sued Washington alleging that mid-1800s treaties guaranteeing tribes the right to take fish also require the state to avoid actions that reduce yields, but that improperly built or poorly maintained culverts under state roads have done exactly that. Some culverts empty back into the steam from too high a height or move water at too high a velocity, others are filled with forest debris.

The case area is roughly the northwestern third of Washington state and its many rivers and streams from which salmon swim to Puget Sound and to which they return – or try to return – to spawn. The federal ruling also includes a much smaller number of culverts overseen by the state Department of Fish and Wildlife, Department of Natural Resources, and Washington State Parks, which must be remedied by 2016.

County, Local Barrier Culverts Are Many, But Not Included
However the targeted state culverts don’t include thousands more in Washington which also pose barriers to salmon passage but aren’t required to be fixed. According to another presentation to the committee last week by DFW, county and local government associations, another 2,264 salmon barrier culverts are operated by county governments and 783 overseen by cities in the case area.

Maximizing Bang-for-Buck
With almost $300,000 in county and local fuel tax revenues DFW will help “inventory, prioritize and study” those barriers with results submitted to lawmakers by the end of June next year. The state, county and local governments are hoping to develop a coordinated approach based on watersheds, “prioritizing work up and down the streams that could have the largest impact on fish recovery.”

SR 530 Fortson Creek WSDOT culvert with new stream crossing - Source: WSDOT

According to a presentation to the committee last week by Shorin of the AG’s Office, the court order directs the state to fix its salmon barrier culverts preferably by avoiding “the need for the roadway to cross the stream” or failing that, by building a “full-span bridge.” The last option is to use a ‘”stream simulation methodology.”

Private Sector Initiative
In the meantime, noted the Department of Natural Resources and the Washington Forest Protection Association in their own presentation to legislators last week, forestry companies and small landowners have spent at least $18 million to repair some 5,142 smaller salmon habitat barriers on private land, but at least 585 such projects remain. To date, 285 salmon barrier culverts overseen by WSDOT have been corrected.

The $2.4 billion estimate for fixing the remaining WSDOT culverts doesn’t include those identified as salmon barriers after the court ruling, nor does it include the 10 percent of the total that the court said can be deferred past 2030.